Challenge:

Modernize Straub Hall’s original single-pane, double-hung windows while preserving the building’s historical appearance, maintaining window operability, and improving thermal comfort and efficiency.

University of Oregon Straub Hall

The University of Oregon completed a major renovation of Straub Hall in 2014, including modernization of the building’s original single-pane windows. Located in Eugene, OR, Straub Hall was originally constructed in 1928 and is described as a prominent historical landmark on the university’s Northeast Central campus. Chosen Windows was selected for the window work because its SLIP attachments helped preserve the building’s historical appearance and window operability while improving thermal comfort and efficiency.
Preserve Straub Hall’s historic exterior appearance.
Improve thermal comfort and efficiency while keeping the windows operable.
Chosen Windows helped the project team evaluate window options, supported the selection of SLIP attachments, completed shop and on-site work, rebalanced the original weight system, and installed the upgraded windows as part of the larger building renovation.
PROJECT TIMELINE
2011–2012
Conception and decision making. Three approaches to the windows on the table.
2012–2014
Window installation, running inside the wider building renovation.
2014
Project completion.

The Project in Four Numbers

The window scope at Straub Hall sat inside a much larger renovation. This is the shape of it.
370
Windows upgraded — 100% of the windows in the building.
Under 1%
Of the $44 million total renovation.
$44 million
Cost of the entire Straub Hall renovation.
9 weeks
370 windows installed floor by floor, October to December 2013.
Figures here are drawn from Chosen Wood Window Maintenance project records and the 2020 NEEA study. Nothing here is derived.

Quick Facts

Building Facts

Location:
Eugene, OR
Size of Building:
83,000 square feet
Built:
1928
Occupancy:
Classrooms, lecture halls, faculty offices
Ownership:
University of Oregon
HVAC system:
Hydronic radiant heating and chilled water cooling

Window Facts

Number of Windows Upgraded:
370 (100% of windows)
Size of Windows:
3 ft wide x 5 ft tall
Window Frames:
Wood
Previous Window Type:
Single-pane and double-hung
Condition of Original Windows:
Excellent
Window Scope Share:
Under 1%
Cost of Entire Renovation Project:
$44 million
Building facts as recorded in NEEA Report #E20-399, 9 April 2020. Window count and cost from Chosen Wood Window Maintenance project records.
A large brick university building with rows of wood windows, seen from its garden entrance

Straub Hall, Built 1928

Straub Hall went up in 1928 and opened as a dormitory. It later became the central home of the university’s Psychology and Linguistics departments, and its four stories of classrooms and lecture halls have made it a prominent historical landmark on the Northeast Central campus.
The university began discussing a major renovation in 2011. The work had to meet what students and faculty actually needed — modern learning spaces, including the university’s first two-story lecture hall, and more floor area — and it had to leave the building looking like itself, the exterior above all. That exterior carried approximately 370 windows.
The mechanical scope moved in the same project: the building’s HVAC was updated during the renovation to match the university-wide hydronic radiant heating system.

What Was Actually Wrong With the Original Windows

At Straub Hall the glass and the joinery were sound — the panes were in excellent condition, the wooden frames in good condition. What had failed was everything around them.
Many of the windows would no longer open. Occupants in those rooms had lost the use of them entirely.
Nothing was weather-stripped. Air came straight through the gaps, and much of the building was drafty in winter.
The cold sat at the perimeter. Before the 2014 renovation, occupants reported that parts of the building felt warm — it has fireplaces — while the rooms nearest the windows felt chilly.
Single-pane and double-hung, throughout. One layer of glass between a classroom and a Eugene winter.
Straub Hall's original arched-head wood windows as they stood before the restoration
Original windows

Who Was at the Table

The windows were a small part of a large project. Four parties made the decision; a fifth, the general contractor, coordinated the work on site.

University of Oregon

The owner, and the main financial decision maker. The university hired us for the renovation work, and its priority was stated plainly from the beginning: the building had to keep its historical appearance.

Rowell Brokaw

The project architects. They also ran the quality assurance checks on the finished windows.

Chosen Wood Window Maintenance

The window restoration and repair company on the team. We put the window options in front of the university and matched each one against what the project was trying to achieve.

Energy Studies in Buildings Laboratory

The university’s own laboratory, on campus. It tested multiple window scenarios empirically to establish the most energy efficient option.

Fortis Construction

The general contractor for the renovation. Fortis coordinated the window scope with every other trade on site.
Team composition per NEEA Report #E20-399, Evergreen Economics, 2020.

Three Ways to Do It, and Why Two Were Dropped

Through the first year of planning, 2011–2012, the team worked the window question three different ways. The rejections are the useful part.
Option 01
Dropped

Complete Window Replacement

What it would have achieved
New double-pane, divided-light windows, built to read as close to the originals once they were in.
Why it was dropped
University officials set it aside. Close was not close enough — the replacements did not match the original design well enough for them.
Option 02
Dropped

Film Added to the Existing Windows

What it would have achieved
Reglaze the existing windows with an insulated film, keeping the original appearance. The frames and panes were in excellent condition, so they could carry it.
Why it was dropped
It was projected to cost more than the other options and to take longer.
Option 03 — Selected

WindowSLIP Attachments

Close-up of a WindowSLIP attachment fitted over an original Straub Hall sash, showing the overlay edge against the historic wood frame
The SLIP overlay pane, fitted to an original sash.
What it would achieve
Less cost than replacement, the look of the original windows kept, and the windows still operable.
Why it was chosen
SLIP was selected because it preserves the original 1928 glass and true divided lites. Insulated glass conversion requires removing the original glass and routing the muntins to accept a thicker unit; SLIP overlays a single tempered Low-E pane on the existing sash and leaves the glazing untouched. The university’s lab confirmed the two perform within two points of each other. Counterweights were rebalanced for the added glass weight, and weight pockets were sealed and insulated per the lab recommendation.
The one real objection
Attachments add weight, and these windows ran on a counterweight system that the added weight could throw out of balance. The counterweights were rebalanced before any sash went back in.
University of Oregon energy lab blower-door rig measuring air leakage on Straub Hall window options
UO Energy Lab testing windows in Straub Hall. Source: NEEA Report #E20-399, Evergreen Economics, 2020.
Infrared thermal image from the University of Oregon Energy Studies in Buildings Laboratory report, showing heat differences across a Straub Hall window
Infrared imaging from the UO Energy Studies in Buildings Laboratory report. Credit: UO ESBL.
INDEPENDENT TESTING

The University Tested Five Scenarios in Its Own Laboratory

The University of Oregon did not take our word for it, or anyone else’s. Its on-campus Energy Studies in Buildings Laboratory tested five scenarios against the same baseline: the existing window as it stood, weatherstripping added, wall insulation added, our SLIP attachments added, and double-pane reglazing — the alternate to SLIP.
SLIP cut the existing window’s U-value by 26%; double-pane reglazing, the alternate, cut it by 28%. Two points apart on the lab’s own numbers.
The lab’s own conclusion: “little difference in conduction performance between the slips and insulated glazing units.” That finding let the team take the cheaper of the two options.
These results are documented in the University of Oregon Energy Studies in Buildings Laboratory’s Straub Hall Envelope Renovation Study, September 2012 — download the lab report (PDF). One thing worth stating plainly: the lab’s SLIP test used sash borrowed from a neighboring window, air leakage went up, and the lab recommended every sash go back into its original frame — which is how we built the job.
MANUFACTURER AND INSTALLER

One Contracted Party for the Whole Window Scope

A window scope is normally split between two firms: a manufacturer builds the units, and a glazing subcontractor installs them. We manufacture and we install, so the University of Oregon handed all responsibility for the windows to one contracted party rather than dividing it between a window manufacturer and a glazing subcontractor.

The Usual Split

A manufacturer supplies the windows. A glazing subcontractor fits them. Responsibility for the finished window is divided between two contracts.

What Happened at Straub Hall

The university put us in charge of installing the windows as well as manufacturing them, so one contracted party carried the whole window scope. We were on site for every stage: the existing wood frames were repaired in the openings, the sashes went back in with the SLIP attachments already fitted, and the sash weights were reworked to carry them.
One contracted party held all responsibility for the windows. The university did not split the scope between a window manufacturer and a glazing subcontractor.
We were on site for every stage. Repairing the existing frames, fitting the SLIP attachments, and reworking the sash weights were all ours.
The rework was ours as well. Other trades occasionally scratched the attachments; we pulled those windows and reinstalled them.

How the Work Was Sequenced

01

Sashes Out, Shop Work in Oregon City

Wide view of the Chosen Wood Window Maintenance shop in Oregon City, with restored Straub Hall sashes on storage racks
We took the existing sashes out and back to our Oregon City shop. That was a deliberate choice: the window scope sat inside a much larger renovation, and shop work was simply easier than working around every other subcontractor on site. At the shop the original sashes were stripped down and the SLIP attachments were fitted.
02

Back to Eugene, Frames Restored in Place

Crew loading window sashes into an enclosed trailer for transport to the restoration shop
The restored sashes were transported back to Eugene. The window frames themselves were not shop work at all — they were restored on site, in the openings.
03

The Counterweight System Rebalanced

Original white-painted sash pulley beside its new metal replacement, the counterweight hardware rebuilt
Attachments add weight, and that was the one objection raised against this option. These windows ran on their original counterweight system, which is what allowed occupants to raise them. That system was rebalanced to carry the added weight before a single sash went back in.
04

Reinstallation, Around the Other Trades

A brick campus building mid-renovation, with a tower crane overhead, site fencing across the frontage and another trade's lift and trailer at the entrance
With the weights rebalanced and the sequence agreed with the other subcontractors — the insulation subcontractor among them — the windows went back in: 370 windows, floor by floor, over nine weeks from October to December 2013. The installation generally went very smoothly. A few attachments did have to come out and go back in a second time: other trades occasionally scratched them.
All photographs: Chosen Wood Window Maintenance.

Who Checked the Work

Not us. The project architects ran the quality assurance on the finished windows.
A visual inspection of the installed windows.
A spray test — a controlled stream of water is played across the glass to prove there is no leak on the inside.
The windows that had come out and gone back in a second time were tested as well. They passed both checks.
Two workers in safety gear inspecting a reinstalled window as part of the quality-assurance check
Inspecting a restored window before sign-off.
Two workers reinstalling a restored sash into a Straub Hall window opening during the project
An example of a window re-installation
The Outcome

What Came of It

The renovation completed in 2014. Everything the university asked us to protect is still there, and the feedback on the windows, and on the wider project, has been universally positive since.
Straub Hall's exterior in summer 2013, all window sashes removed for shop restoration
Summer 2013 — sashes removed for shop restoration.
Straub Hall's finished elevation after restoration, the original windows back in their openings
After — restored windows back in their original openings.

The building still looks like itself.

Straub Hall was upgraded without changing its face. The original windows and wooden frames stayed where they were, so the elevation reads exactly as it did before.

The windows still open.

Operability was one of the reasons attachments beat replacement here. The counterweights were rebalanced before the sashes went back in, so every window still works by hand.

The cold rooms warmed up.

The rooms nearest the windows were chilly before the renovation. Thermal comfort was the stated aim, and the university got it with the appearance and the operation kept.
“Based on the energy modeling that we did for the building, including live mock ups, the study showed that the SLIPS were very close to the energy performance of the IGU option, and given the lower cost the decision was made to go with the SLIP system. We are now three years into occupancy and have had no issues with the windows. The SLIPS are very unobtrusive, and we were able to save hundreds of historic windows and still met our stringent standards of energy performance that exceeds Oregon State Code.”
George Bleekman, Owner’s Representative, Capital Design & Facilities Management, University of Oregon
Quality That Earns Trust
They came back.
Since finalizing this project, the university has come back to us for ten more campus buildings, including Gerlinger Hall, Villard Hall, Friendly Hall, and the Volcanology building. A proof point that our quality earns trust!
Twelve years since completion, the numbers hold up:
12 years in service, zero callbacks.
The sash were 85 years old and unrestored when we received them.
Straub Hall is LEED Gold. UO reported the building performs 35% better than Oregon Energy Code requires, with the original windows in the envelope. (Source: UO news release, January 22, 2015.)

Is a Window Attachment Right for Your Building?

Straub Hall is not a template. The 2020 study’s own reading of its interviews is that secondary window attachments have potential in three situations.
And the limit, in the study’s own conclusion: window attachments may not be the appropriate solution for every building. At Straub Hall the case was made by two things together — the university’s commitment to preserving the building, and the excellent quality of the windows and wooden frames that were already there. If your building has one of those and not the other, tell us, and we will say so.
Windows with historic or sentimental value.
Windows that need to be operated.
Windows with wooden or steel frames.
Two Chosen Wood Window Maintenance crew members in branded orange sweatshirts repairing a wood window in a Pacific Northwest home.

Why Work with Chosen

We restore rather than replace, on buildings where the original is worth keeping. That has been the work since 1998 — from a single sash to landmark buildings — out of Oregon City and Seattle.
Restoring wood and steel windows since 1998 — more than 25 years of it, across the Pacific Northwest.
Award-winning preservation work: Restore Oregon’s DeMuro Award, Historic Seattle awards, and more.
Accredited and affiliated — the Better Business Bureau, Historic Seattle, Restore Oregon, the Association for Preservation Technology, and Energy Star.
Safe on older buildings — we work to EPA Lead RRP and OSHA standards, with full lead and asbestos containment.

Specifications and Downloads

Full documentation for anyone specifying, permitting, or building from this job — every item below downloads directly.
Section 08 01 52.93 — Historic Treatment of Wood Windows (guide spec).
Section 08 80 10 — Window Attachments / SLIP.
UO ESBL Straub Hall Envelope Study, the University of Oregon lab report (PDF).
NEEA Report E20-399, the market characterization study this case study cites.