Challenge: Restore historic steel and wood window assemblies while retaining original 1931 material, preserving historic profiles, complying with the regulations for asbestos-containing glazing putty, and supporting long-term durability.
Saint Edward Seminary
As part of the 2019–2020 restoration of the 1931 Saint Edward Seminary in Kenmore, Washington, overlooking Lake Washington, Chosen Wood Window Maintenance implemented a preservation-driven rehabilitation process for the building’s historic steel and wood window assemblies. The project included nearly 19,000 square feet of historic window assemblies and emphasized material retention, regulatory compliance, and long-term durability.
Primary objective. Retain as much original 1931 window material as possible.
Secondary objective. Preserve historic profiles while supporting long-term durability.
The project required a systematic process that included documentation, controlled removal, regulated transport, shop restoration, repair, reglazing, finishing, and final reinstallation for both historic wood and steel window assemblies.
The Project in Four Numbers
The window scope at Saint Edward Seminary ran across the whole building, in two materials. This is its shape.
19,000
Square feet of historic window assemblies, restored and kept in service.
438
Total window units restored or fabricated.
909
Historic sashes rehabilitated.
2,462
Total lites restored or fabricated.
Across 34 or more distinct window configurations, in historic wood and steel.
Quick Facts
Building Facts
Location:
Kenmore, Washington
Setting:
Overlooking Lake Washington
Built:
1931
Architect:
John Graham Sr.
Building size:
75,000 square feet
Listed:
National Register of Historic Places; Washington Heritage Register
Before restoration:
Washington Trust for Historic Preservation Most Endangered list
Restoration:
2019–2020
Historic window assemblies:
Nearly 19,000 square feet
Restoration shop:
Oregon City, Oregon
Window Facts
Window materials:
Historic wood and steel
Total window units:
438 restored or fabricated
Wood windows:
414 — 405 restored, 9 newly fabricated
Steel windows:
24 — 18 restored, 6 fabricated to match and installed
Historic sashes rehabilitated:
909
Total lites:
2,462 restored or fabricated
Window configurations:
34 or more distinct configurations
Building and window facts as recorded for the Saint Edward Seminary window rehabilitation, Kenmore, Washington.

Saint Edward Seminary, Kenmore, Washington — brickwork and arched window openings on the original 1931 elevation
Saint Edward Seminary, Built 1931
Saint Edward Seminary opened in 1931 on a bluff above Lake Washington in Kenmore, Washington. Its windows are original to it — historic assemblies in two materials, wood and steel, across a building whose elevations were designed around them.
The 2019–2020 restoration of the building put nearly 19,000 square feet of those assemblies back into service: eight months on site, January to August 2019, 4,450 field hours, with the new steel units following in 2020. Chosen Wood Window Maintenance implemented a preservation-driven rehabilitation process for all of them, wood and steel alike.
The approach was set by what the building is. Material retention came first, regulatory compliance ran through every phase, and the finishing systems were chosen for long-term durability rather than for speed.
What Saint Edward Seminary Needed
The building’s architectural integrity depended on the windows staying in it. Six requirements shaped the restoration strategy.
No window specification existed for the project. Chosen wrote the restoration plan: a step-by-step sequence of activities for the wood windows and a separate one for the steel, naming every product, containment procedure, and reinstallation step. Lydig Construction submitted it as the project standard, and the work was built to it.

Who Was at the Table
The windows were one part of a much larger restoration of the building. Five parties shaped the project around them.

Washington State Parks
The owner. The seminary sits in Saint Edward State Park, and the building had to come back into use still looking like the landmark the state had taken on.

Daniels Real Estate
The developer, who took the building on and carried the restoration through to a working hotel.

Ron Wright & Associates
The project architect, responsible for how the restored building went back together around its original openings.
Lydig Construction
The general contractor. Lydig submitted Chosen’s restoration plan as the project standard and coordinated the window scope with every other trade on site.

Chosen Wood Window Maintenance
The window restoration contractor. Chosen wrote the restoration plan the project was built to, restored the steel in place and the sash in its Oregon City shop, and returned every unit to its own opening.
Have a building whose original windows are worth keeping?
REPAIR OVER REPLACEMENT
Original 1931 Material, Kept in the Building
Chosen Wood Window Maintenance used a structured process for both historic steel and wood windows, beginning with documentation and controlled removal before moving into shop restoration, repair, reglazing, finishing, and reinstallation.
Historic Wood
405 historic wood windows were restored and 9 new custom wood windows were fabricated, for a total of 414 wood windows.
Historic Steel
18 historic steel windows were restored and 6 new steel windows fabricated to match and installed, for a total of 24 steel windows.
What Was Installed
The products that went back into the openings, by material.
A Preservation-Driven Restoration Process

The window assemblies came out documented, protected, and ready for regulated transport and restoration.
PHASE 01
On-Site Documentation and Controlled Removal
Each window assembly was documented before removal so the work could be tracked and returned to the correct location. Steel windows were cataloged and tagged, and wood sash were labeled for precise reinstallation.
Every window was tagged with the general contractor’s floor-plan number before removal and photographed from the interior with the number visible. Each sash was stamped in a concealed spot on the stile, bagged and cataloged by number, and after restoration matched to its mate and staged by number for the return trip.


Decades of coatings came off — the steel frames in the opening, the sash in the shop — and the original steel profiles and wood joinery came through preserved.
PHASE 02
Shop Intake and Stripping
The steel frames never left the building. Only the operating steel sash and the wood sash travelled to Oregon City, where they went through intake inspection, documentation, hardware removal, and dip-tank stripping to remove old coatings, paint, putty, and glass.
Stripping was done only by asbestos-certified employees in a contained stripping room, with sash immersed 24 hours in a 1,500-gallon dip tank. Washington and Oregon DEQ were notified before every transport, sash moved in sealed asbestos-labeled bags in a closed vehicle, and Waste Management took custody of the stripping waste with a written receipt.

PHASE 03
Repair and Structural Rehabilitation
After stripping, the assemblies were repaired and stabilized using methods appropriate to the material and condition of each unit — the steel frames in place under the scaffold, the sash in the shop.
Historic steel and wood assemblies were stabilized, with repair and material retention taking priority over replacement.

PHASE 04
Priming, Reglazing, Finishing, and Reinstallation
The final phase included priming, reglazing, weatherstripping, finishing, and returning the sash to their original openings.
The restored sash came back to site, went into their original openings, and were adjusted for operation and sealed at the parting beads.
Planning a restoration on a building with original windows?
The Outcome
What Success Looked Like
Nearly 19,000 square feet of historic window assemblies went back into service, and the architectural integrity of Saint Edward Seminary was preserved.

Original material stayed in the building.
The restoration strategy emphasized maximum retention of original 1931 material and repair over replacement.
The historic profiles were preserved.
Glazing was tooled to match the historic profiles, and replacement components were used only where the original was beyond repair.
909 sashes went through the shop.
Chosen restored or fabricated 438 total window units, rehabilitated 909 historic sashes, and restored or fabricated 2,462 total lites across 34 or more distinct window configurations.
The methodology allowed nearly 19,000 square feet of historic window assemblies to remain in service while preserving the architectural integrity of Saint Edward Seminary.
Historic window assemblies kept in service — Saint Edward Seminary, 2019–2020
Regulated End to End
Certified handling, every phase.
Containment protocols, labeled asbestos-rated transport bags, certified hazardous material handling in contained stripping rooms, and DEQ compliance procedures ran through the work from removal to reinstallation.
Project Gallery
The restored wood and steel windows back in the building at Saint Edward Seminary.

Why Work with Chosen
We restore rather than replace, on buildings where the original is worth keeping. That has been the work since 1998 — from a single sash to landmark buildings — out of Oregon City and Seattle.
25+ Years of Happy Customers
Our Work
Contact Chosen Wood Windows Today
Fill out the form below, or give us a call now to move forward with your window restoration.
We look forward to meeting you.
We look forward to meeting you.